Ljubljana Thermal Power Plant

Facility name

Ljubljana Thermal Power Plant

Investor / Client

ENERGETIKA LJUBLJANA d.o.o.

Location

Ljubljana, Slovenia

Time period

1962-2024

Facility size / Capacity

Installed power: Unit 1 in 2: 2 x 42 MWel, 188 MW; Unit 3: 50 MWel, 124 MWt; GT 1 in 2: 2 x 53 MWel

General

Electricity production in Ljubljana began as early as 1898 in the so-called Old Power Plant on Slomškova Street. The importance of the facility for Ljubljana was reduced with the construction of the transmission lines, which enabled electricity to be supplied from the Velenje TPP (1931) and later the reliability of the supply to Ljubljana was further increased with the supplies from the Trbovlje TPP (1939) and the Brestanica TPP (1943).


The old power plant in Ljubljana was converted into a boiler house in 1961, replacing some of the individual heating facilities in the city centre. Since 1966 it has been replaced by the new Thermal Power Plant (TE-TOL) at the Moste site.

General

Challenges and specifics

The technological equipment of today's facilities is adapted to the role in the heating system of the city of Ljubljana, where the Moste site covers about 90% of district heating needs. The base was formed by three coal-fired units, which were adapted to operate with a more environmentally acceptable fuel during the course of their operation. A large heat storage facility has also been built to optimise heat and electricity production. The further development of TPP Ljubljana (TE-TOL) and Energetika Ljubljana is based on the production of heat and electricity from two gas turbines in a closed cycle. The two turbines can be operated with both natural gas and extra-light fuel oil for greater flexibility and the possibility of participating in the regulation of the electricity system. Energetika Ljubljana also has a large thermal consumption capacity, which potentially allows for construction of a waste-to-energy facility in central Slovenia in compliance with today's energy efficiency norms and the most demanding ecological standards.

Challenges and specifics

IBE services

IBE has played an active role as a designer in the TPP (TE-TOL) facilities since TPP  inception in the 1960s.

1962–1966

Installation of the first coal-fired unit UNIT-1, with an electrical capacity of 42 MW and a 94 MW heat station for heating the city of Ljubljana.

IBE produced the project documentation and advised the client on solutions.


1963–1967

Installation of the second coal-fired unit UNIT-2, with the same parameters.

IBE prepared the project documentation and advised the client on solutions.


1980-1984

Installation of the third coal-fired unit UNIT-3, with an electrical capacity of 50 MW and a 124 MW heating station for the heating of the city of Ljubljana.

IBE produced the project documentation.


1995-1996

Installation of a 25,000 m3 heat accumulator.

IBE produced the project documentation.


2004

Installation of two gas-fired units, capacity in the order of 50 MW, combined process.

IBE produced the project documentation.


2018 - 2024

Installation of two 53 MW gas-fired units, closed cycle.

IBE prepared the project documentation for the client, the supplier of the main process equipment and carried out certain execution works.





Similar reference projects:

Boštanj Hydropower Plant

Boštanj Hydropower Plant

Litostroj Substation

Litostroj Substation

Krško Nuclear Power Plant

Krško Nuclear Power Plant

Back to list
Back to top