Krško Nuclear Power Plant
Facility name
Krško Nuclear Power Plant
Investor / Client
NEK d.o.o.
Location
Krško, Slovenia
Time period
1983 -
Facility size / capacity
Rated power: 727 MW
The Krško Nuclear Power Plant is key to ensuring stable electricity production in Slovenia, with operational safety being its highest priority.
General
The Krško Nuclear Power Plant, which began commercial operation in 1983, is the only nuclear power plant in Slovenia. With its 727 MW pressurised water reactor, it contributes 696 MW of electricity to the grid. Operational safety is the first and highest priority, which is undoubtedly crucial for the operation of the plant. The Krško NPP has a significant impact on energy coverage, as it meets a share of the electricity demand in Slovenia and Croatia. Krško NPP ensures stable production of low-carbon electricity for reliable supply to consumers.
IBE services
Calculated upgrades of equipment and processes are constantly needed to achieve impressive operational results.
IBE has been present with its services since the very beginning of NEK's construction. Throughout the years of operation, IBE has produced a range of DMP (design modification package) documentation and TOP (turnaround package) documentation for the client for design modifications to the power plant, and provided support to the contractors during the implementation phase of the design changes, as well as the preparation of FDCR (field design change request) documentation.
In addition to the preparation of the design change documentation, IBE played a leading role as external experts in the preparation of the documentation for the extension of the NPP lifetime from 40 to 60 years, which will allow the Krško NPP to operate until 2063.
An Environmental Impact Assessment was carried out for the lifetime extension and cross-border consultations were held with all 4 neighbouring countries and Germany in the process of approving the lifetime extension.
IBE services
Throughout the years of operation, IBE has been producing documentation for the client for project modifications (DMP, ABD, TOP). The list of modifications carried out is extensive, but below is an overview of those in which we have played a key role since 2014:
| 2023 | Comprehensive upgrade of lightning protection at NEK (Mod. 1252-EE-L) |
| 2023 | Technical protection of the dry storage building (Mod. 1268-TZ-L) |
| 2022-2023 | Replacement of heat exchangers CC101HEX-001 and CC101HEX-002 |
| 2022-2023 | NE Krško - TSV; NEW BUILDING, ADDITION, RECONSTRUCTION |
| 2021-2023 | Installation of a lift in the Radioactive Cargo Storage Building (RWSB), mod. 1283-HE-M |
| 2018-2023 | ECRTCS HVAC and Habilitation Systems; Mod. 1058-VA-L |
| 2018-2023 | ECR and TPC Technical Security (Mod. 1069-TZ-L) |
| 2017-2023 | Krško Nuclear Power Plant / Dry Spent Fuel Storage; NEW BUILDING |
| 2017-2023 | Reconstruction of BB1 and construction of new cable connections (mod. 1027-NA-L) / Reconstruction of BB1; ADDITION, NEW BUILDING, RECONSTRUCTION |
| 2017-2023 | Reconstruction of building BB1 and construction of new cabling (mod. 1027-NA-L) / Redesign of building SU to accommodate simulated ECR; NEW BUILDING, RECONSTRUCTION |
| 2016-2023 | Replacement of the sensor system of the NPP outer fence, mod. 1131-TZ-L |
| 2022 | Modernisation and upgrade of PARMS radiological monitors |
| 2020-2022 | Reconstruction of the Operational Support Centre - OPC (mod. 1056-NA-L); NEW BUILDING |
| 2016-2022 | Technical protection of the RD lock overhaul depot, mod. 1092-TZ-L |
| 2019-2021 | Krško Nuclear Power Plant; NEW BUILDING |
| 2017-2021 | NEK Safety Upgrade - Project BB2 / Building BB2; NEW BUILDING |
| 2020 | Improvement and simplification of the islanded power supply to LR NEK from TEB (Mod. 1240-SY-L) |
| 2019 | Replacement of T3 60 MVA 110/2x6.3 kV transformer and subsystems (mod. 1095-XR-L) |
| 2019 | Reconstruction of the Operational Support Centre - OPC (mod. 1056-NA-L) / Kineta between OPC and Administration Building; NEW BUILDING |
| 2018-2019 | Mod. 1095-XR-L; Construction of foundation with oil pit for transformer T3 / Foundation for replacement transformer T3; NEW BUILDING |
| 2018 | Upgrade of communication systems at NEK (Mod. 1053-PC-L) |
| 2018 | NEK Safety Upgrade - Project BB2 / Construction Pit; NEW BUILDING |
| 2015-2018 | Construction of cable connections between the auxiliary building (AB-MHE30) and the bunker building (BB1); NEW BUILDING |
| 2013-2018 | Equipment and Radioactive Cargo Handling Building (WMB); NEW BUILDING, DEMOLITION |
| 2016 | Transfer of full power from 1000 kVA generator to LD11 collector, mod. 1148-EE-L |
| 2016 | Upgrade of condenser tube cleaning system (mod. 723-CW-L) |
| 2013-2015 | NE Krško - Measures to maintain the flood safety of NEK |
| 2013-2014 | NPP Krško / Replacement of DC circuit breakers, modification no. 666-DC-L, rev. 0 |